SAP C_TS422_1909 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing" certification exam validates that the candidate possesses the fundamental and core knowledge required of the SAP S/4HANA Manufacturing consultant profile. This certification proves that the candidate has an overall understanding and inādepth technical skills to participate as a member of a project team in a mentored role.
C_TS422_1909 Exam Certification Details:
| Level: | Associate |
| Languages: | German, English, French, Chinese |
| Duration: | 180 mins |
| Exam: | 80 questions |
| Cut Score: | 55% |
| Sample Questions: | SAP C_TS422_1909 Exam Sample Question |
NEW QUESTION 46
What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.
- A. Past procurement quantities
- B. Past quotation quantities
- C. One-off events
- D. Market intelligence
- E. Past sales order quantities
Answer: C,D,E
NEW QUESTION 47
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?
- A. Forecast planning
- B. Consumption-based planning
- C. Manual planning without check
- D. Material requirements planning
Answer: B
NEW QUESTION 48
You want to perform capacity availability checks on your production orders. What must be set for this to occur? Note: There are 2 correct answers to this question.
- A. Checking rule and group must be assigned.
- B. PRT Availability check must be set.
- C. Indicator Relevant for finite scheduling must be set.
- D. Checking control must have an overall profile assigned in customizing.
Answer: C,D
NEW QUESTION 49
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?
- A. The planned order is converted to a production order.
- B. The planned order's components are copied from the picking list.
- C. The planned order's component availability is checked
- D. The planned order generates capacity requirements.
Answer: D
NEW QUESTION 50
What are some of the SAP Fiori user types?
There are 3 correct answers to this question.
Response:
- A. Expert
- B. Occasional
- C. Business partner
- D. Employee
- E. Developer
Answer: A,B,E
NEW QUESTION 51
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?
- A. Resource network
- B. Setup matrix
- C. Work center hierarchy
- D. Operation network
Answer: C
NEW QUESTION 52
What capabilities does SAP S/4HANA embedded analytics provide?
There are 2 correct answers to this question.
Response:
- A. Strategic analysis
- B. Automatic update of story boards
- C. Real time decision support
- D. Comparison of current data with historical data to identify trends
Answer: A,C
NEW QUESTION 53
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. By industry
- B. By period
- C. By material type
- D. By plant
Answer: B,D
NEW QUESTION 54
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Functional Location BOM
- B. Class BOM
- C. Work Center BOM
- D. Sales Order BOM
Answer: A,D
NEW QUESTION 55
Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider? Note: There are 2 correct answers to this question.
- A. The maximum mater all number length is 40 for external numbers and 18 for internal numbers.
- B. In Customizing you can decide by material type whether to use the long material number.
- C. The display template for material numbers applies to all clients.
- D. The number of leading zeros for internal numbers is client-specific.
Answer: A,C
NEW QUESTION 56
Which times are used for Basic Date Scheduling of manufacturing planned orders in MRP?
There are 2 correct answers to this question.
Response:
- A. Float before and float after production
- B. Opening period
- C. Goods receipt processing time
- D. Setup time
Answer: A,D
NEW QUESTION 57
Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What is the impact of this decision? Note: There are 3 correct answers to this question.
- A. Sales order-specific stock is created
- B. Sales order-specific planning run is required.
- C. Net requirements calculation is sales order-specific.
- D. Production orders are created with sales order reference.
- E. Storage location MRP areas are required.
Answer: A,C,D
NEW QUESTION 58
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.
- A. Product-related
- B. Cost-related
- C. Order-related
- D. Milestone-related
Answer: A,C
NEW QUESTION 59
Which of the following are capabilities of multidimensional reporting in SAP S/4HANA embedded analytics?
There are 3 correct answers to this question.
Response:
- A. Scheduling
- B. Sort
- C. Filters
- D. Forecast
- E. Drilldown
Answer: B,C,E
NEW QUESTION 60
The material master of your finished product contains MRP type "PD". You set a manual firming date in the stock requirements list. Which of the following will firm planned orders" There are 2 correct answers to this question.
Response:
- A. Creating a planned order within the planning time fence
- B. Assigning a production scheduling profile
- C. Setting a planning time fence in the Material Master Record
- D. Manually changing the quantity of a planned order
Answer: A,C
NEW QUESTION 61
What is a work center hierarchy in SAP S/4HANA capacity planning?
- A. A group of work centers in a parallel sequence that is used to split product on quantities and work on them in parallel
- B. A group of alternative work centers providing a cumulative available capacity for production
- C. A group of work centers in a production line being used in sequence for production
- D. A group of alternative work centers for production, structured in hierarchy levels by prior ties
Answer: B
NEW QUESTION 62
In your project, you have several materials that are planned by different people. How can you assign the planning responsibility?
- A. MRP group
- B. MRP controller
- C. MRP planning file
- D. MRP type
Answer: B
NEW QUESTION 63
Which of the following is an advantage of MRP Live and NOT available in classical MRP?
Response:
- A. MRP Live can create production orders automatically
- B. MRP Live can priorities demand from sales orders
- C. MRP Live can plan materials with recursive BOMs
- D. MRP Live can propose alternative solutions
Answer: D
NEW QUESTION 64
You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?
- A. Scheduling working time only
- B. Squeezing
- C. Insert operation
- D. Find Slot
Answer: D
NEW QUESTION 65
......